Project Timeline
- Where is the project now?- 
                           
                           Spring 2023 
 The project is in the final phases of construction and is on schedule to open on July 1, 2023, in time for the fall 2023 football season.
 
- 
                           
                           
- Project timeline- 
                           
                           February 7, 2018 - . 
 June 5, 2019 - Ceremonial bench removal marks beginning of demolition on east side of CEFCU Stadium.
 February 2020 - Spartan Athletics partners with Webcor and HOK to design and build the new Spartan Athletic Center.July 2020 - Removal of the east side hill at CEFCU Stadium. 
 November 17, 2020 - CSU Board of Trustees votes to approve building plans. Construction begins.
 Summer 2023 - Project completion and official opening.
 
-